Applications have been submitted for lands located in northwest Newmarket, south of Davis Drive West between Yonge Street and Bathurst Street. We received applications for an Official Plan Amendment, a Zoning Bylaw Amendment and a Draft Plan of Subdivision to permit a proposed residential community. The applicant is proposing to amend an existing land use currently designated in the Town of Newmarket Official Plan, 2006 as Parks and Open Space to the following land use designations - Stable Residential, Emerging Residential, Urban Centre, and Commercial. The applicant is proposing to amend the Town's Zoning By-law, 2010-40 in the following ways:
- A zone change from Open Space Two to Residential One (R1-D);
- A zone change from Open Space Two to Residential One (R1-CP);
- A zone change from Open Space Two to Residential Four (R4-CP);
- A zone change from Open Space Two with a site specific exceptions (OS-2-32) to Residential Five (R5-__) with a site specific exception requested for a high density residential block; and
- A zone change from Open Space Two to Retail Commercial 2 (CR-2-__) with a site specific exception to allow a motor vehicle service station as an additional use.
Public Information Centres and Public Input Opportunities
The following are past and present Public Information Centres and Public Input Opportunities for the Glenway Project.
Townhouses Site Plan Application (former clubhouse; block 159 on plan) | Tuesday, February 24, 2015 - 6 to 8 p.m. Cane A & B Room at the Municipal Offices - drop in - no presentation | landscaping, fencing, building massing, building materials, access/parking, EMS/Fire access |
Subdivision | Spring 2015
| Interface Compatibility Plan, Grading (stormwater management areas, residential lots, open spaces), tree relocation/landscaping, Sidewalk and trail locations |
Lesson's Learned (Facilitated Session) | Spring 2015 | OMB decisions and related matters, strategic property consideration/land acquisition, role of various parties |
Future Site Plan Applications for commercial and residential site plan blocks (blue and yellow areas on map) | TBD | Landscaping, fencing, building massing, building materials, access/parking, EMS/Fire access |
Glenway West Subdivision Application | TBD (Statutory Public Meeting following the development application submission) | Compatibility, parkland dedication, engineering requirements (traffic stormwater management, servicing, grading etc.) zoning (setback, driveway lengths, building height, lot coverage etc.) tree preservation. |
Glenway West Site Plans (for any residential condominium blocks) | TBD (Future site plan PICs if directed by the Site Plan Review Committee) | Landscaping, fencing, building massing, building materials, access/parking, EMS/Fire access. |
Lessons learned and questions from the Glenway Public Information Centre
Public Information Centre Display Materials (May 26, 2015)
Grading Plans
Cross Sections
Landscape Plans
Settlement Offer and Supporting Studies, November 20, 2013) - without prejudice
October 2013
Second Settlement Offer (November 20, 2013)
Settlement Offer (August 23, 2013)
On August 23, 2013 a Settlement Offer was provided by the solicitors for Marianneville Developments Limited relating to the OMB appeals for the proposed redevelopment of the Glenway Golf Course lands. The following documents are provided below: the Settlement Offer letter from the developer's Solicitor, a revised Draft Plan of Subdivision, Revised Official Plan amendment, Revised Zoning By-law amendment and parkland schematic.
Marianneville Developments Limited has provided responses to resident concerns and comments received at a Public Meeting on January 7, 2013, as well as responses to written comments received by the Town as outlined in the below Comment Matrix.
Revised Stormwater Management Submission (July 2013)
Original Submission for the Glenway Application
Notice of Hazard Trees Removal
Please be advised that a number of trees within the Glenway golf course property have been identified as hazard trees and are proposed to be removed on August 24, 2013 by the owner of the property. These 15 trees have been assessed and reviewed by the Town's peer review arborist who agrees with their removal. The trees will be taken down in accordance with good arborist practices and will take approximately one day. We understand the contractor may be moving equipment on site on Friday 23, 2013.
For additional information or copies of any of the documents listed, please contact the Planning Department.